Please contact us if you wish to receive more information on the below projects.

Contact: Uwe Berg, Finances / Sales

Wind Energy Converter   Wind speed  Net prod. /a  Stage 
4 x DeWind 1MW
and
2 x DeWind 1.25MW  
5.9 m/s   12,000 MWh   Building permits granted
Scheduled time of initial operation: mid-2004 
       
5 x Vestas 850kW   5.4 - 5.6 m/s   5,395 MWh   Building permit granted
Scheduled time of initial operation: Apr-June 2004    
       
23 Enercon 1.8MW   6.0 m/s   63,825 MWh   Building permit expected to be granted in Jan-March 2004
Scheduled time of initial operation: end of 2004 
       
15 GEwind 1.5MW   6.3 m/s   45,560 MWh   Building permit expected to be granted soon
Scheduled time of initial operation: end of 2004    
       
4 x Vestas 2 MW  6.5 m/s   17,521 MWh   Initial operation: February 2004   
       
19 x Vestas 2MW  6.3 m/s   70,300 MWh   Building permit expected to be granted soon
Scheduled time of initial operation: Jul-Sep 2004   
       
2 x SüdWind 1.5 MW   6.1 m/s   5,800 MWh   Building permit granted
Initial operation: Mid-2004    
       
1 x Enercon 600KW  6.1 m/s   1,150 MWh   Building permit expected to be granted soon
Scheduled time of initial operation: Apr-June 2004    